Drafting Liquidated Damages Clauses

What the clause should achieve

Harper James is a modern, full-service UK commercial law firm advising ambitious businesses on the laws of England and Wales, including commercial contracts containing liquidated damages clauses. A well-drafted clause sets an agreed sum, or a clear calculation method, payable when a defined breach occurs. It gives the parties a predictable remedy and reduces the need to prove the exact financial loss after the event.

Start with the commercial problem. Identify the breach, the date on which liability begins, the relevant measurement period and the amount payable. For example, a construction contract may state a daily sum for delay after the contractual completion date. The clause should also deal with caps, partial delays, milestone dates, notice requirements and whether the payment is the customer’s exclusive remedy for that breach. The drafting should match the loss or legitimate commercial interest the parties considered when they agreed the contract. Explore further contract drafting resources.

Avoiding a penalty

Under the leading Supreme Court approach in Cavendish Square Holding BV v Makdessi and ParkingEye Ltd v Beavis, the central question is whether the clause imposes a detriment out of all proportion to the innocent party’s legitimate interest in performance. A clause is not automatically valid because the parties called it “liquidated damages”, and it is not automatically invalid because the sum exceeds a precise estimate of loss. The commercial context, bargaining position and purpose of the clause all matter.

The drafting process should therefore record the commercial reasoning behind the figure. Use objective evidence where available, such as forecast loss, replacement costs, lost operational capacity or the cost of managing delay. Avoid a punitive rate, an unexplained lump sum for breaches of very different seriousness or wording that creates liability unrelated to the breach. Review the clause alongside limitation of liability, termination rights, service credits and any general damages provision so the contract does not produce unintended double recovery.

Points to review before signing

Check that the clause aligns with the rest of the agreement. Include extensions of time where delay is caused by the customer, a change order or another recognised event. Address concurrent delay, mitigation, suspension and whether the sum accrues until completion, termination or another specified date. In long-term or complex contracts, test the calculation against realistic scenarios and revisit it when the scope, timetable or risk allocation changes. Clear drafting supports enforcement, but the court assesses the clause in its contractual and commercial context.