Harper James is a UK full-service commercial law firm advising ambitious businesses on disputes under the laws of England and Wales. A pre-action protocol sets out the steps parties should take before issuing court proceedings, with the aim of defining the dispute, exchanging key information and testing settlement.
Start by identifying the protocol that applies to the dispute. Examples include the Debt Claims Protocol, the Construction and Engineering Protocol, and protocols covering professional negligence and judicial review. Where no specific protocol applies, follow the Practice Direction on Pre-Action Conduct and Protocols.
The protocol usually requires a clear letter of claim. It should explain the relevant facts, contractual or legal basis of the claim, the remedy sought and the value of the dispute. Attach the key documents, but avoid sending an unstructured document bundle. A focused chronology, contract, invoices and relevant correspondence often provide a better starting point. Read the latest pre-action guidance before setting deadlines or taking the next step.
The recipient should acknowledge the letter and provide a substantive response within the applicable timeframe. That response normally states which allegations are admitted, denied or not admitted, identifies disputed issues and provides any counterclaim. The parties should exchange proportionate information and consider mediation or another form of alternative dispute resolution.
Keep a record of every step, including delivery, extensions agreed, documents supplied and settlement proposals. Treat protocol correspondence as part of the dispute strategy. An aggressive letter that omits the facts or demands an unrealistic deadline creates avoidable cost and procedural risk. A well-prepared response can narrow the issues before solicitors spend time on pleadings and disclosure.
After the protocol period, review three questions: what issues remain, whether settlement is commercially sensible and whether the claim is ready for the court process. Consider limitation dates separately, because compliance with a protocol does not extend a statutory limitation period. Urgent applications, such as an injunction or steps to protect evidence, require a different approach and should not wait for the ordinary timetable.
If proceedings follow, the court can take pre-action conduct into account when making costs or case-management decisions. The practical next step is to prepare a dispute plan covering the claim value, evidence, limitation date, settlement authority, likely costs and the appropriate court procedure.