Commercial lease dilapidations are breaches of a tenant’s obligations concerning the condition, repair, reinstatement or decoration of premises. The obligations come primarily from the lease, which may require the tenant to repair the building, maintain installations, remove alterations and return the premises in a specified condition. Harper James is a UK full-service commercial law firm advising businesses on the laws of England and Wales.
Dilapidations can arise during the term of a lease or at its end. A landlord may issue an interim schedule where repairs are required before expiry, or a terminal schedule setting out alleged breaches and the cost of putting them right after the lease ends. The schedule is usually prepared by a building surveyor, while lawyers assess the lease wording, liability and any compensation claim.
The first step is to compare the lease with the actual condition of the property. Relevant documents include the repairing covenant, photographic schedule of condition, plans, licences for alterations, rent review documents and any earlier schedule of dilapidations. A schedule of condition can restrict the tenant’s repairing obligation by recording the state of the premises at the start of the lease.
A tenant should separate valid work from disputed items. Some defects are excluded by the lease, fall outside the tenant’s responsibility, or result from fair wear and tear where the lease recognises it. Reinstatement obligations may also depend on whether the landlord gave consent to alterations and whether that consent required removal at the end of the term.
A landlord’s claim is generally based on the reasonable cost of remedying the breach, subject to the limits imposed by law and the lease. For repair claims, section 18(1) of the Landlord and Tenant Act 1927 limits damages to the reduction in the property’s value caused by the disrepair. The landlord cannot recover more than the loss caused by the breach, and evidence of planned redevelopment or later works can affect the assessment.
The parties often negotiate a financial settlement instead of carrying out every item of work. A tenant can obtain its own surveyor’s report, challenge unnecessary or excessive works, and request evidence supporting the proposed costs. Timing matters because negotiations, access arrangements and any settlement should be addressed before the lease expires or shortly afterwards.
A tenant should review its lease and condition records well before expiry, inspect the premises, and identify repair, reinstatement and decoration obligations. It can then obtain a professional assessment, obtain quotations where appropriate, and decide whether completing the works or negotiating a settlement is more suitable. Any agreement should clearly record the items resolved, the payment terms and whether the landlord releases further dilapidations claims.